Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 25, 2023 - 06:00 UTC
Scheduled
Start time : 25/09/2023 06:00 UTC End time : 25/09/2023 15:00 UTC Service impact : At the end of the maintenance, some servers in racks 42A06, 42C05, 42C13, 42D21 and 42E17 will undergo a soft shutdown Service improvement : Following our continuous improvement policy, we are doing some electrical works in RBX3
Posted Sep 12, 2023 - 17:15 UTC
This scheduled maintenance affected: Dedicated Servers || Global Infrastructure (RBX).